Contract Termination Rights for Builders in WA
When a WA builder may lawfully walk away. The HBCA gives builders almost no statutory exit, and Home Indemnity Insurance does not respond when a solvent builder abandons a job.
What it is
Termination is where a WA builder is most exposed, because the Home Building Contracts Act 1991 (WA) hands the builder almost nothing. The Act's termination machinery in section 19 runs one way. It applies where a party may terminate under section 4(5), section 10(4), section 14(3) or Schedule 1. Every one of those is an owner's right and none of them is the builder's: the first three follow a builder's failure, and the fourth follows a price increase the owner declines to wear.
The builder's grounds live in the contract. WA law leaves them there.
The contractual grounds
A WA home building contract has to write its own default and termination regime. There is no statutory completion date, no statutory extension of time mechanism and no statutory list of default events. Whatever the contract says still has to survive section 15(1)(b), which prohibits provisions that are unconscionable, harsh or oppressive, and section 28, which voids any arrangement that modifies the Act to the owner's disadvantage.
The one statutory exit the Act protects
Section 15(3) is the exception worth knowing. A contract provision must not be called in question as unconscionable, harsh or oppressive by reason only that it entitles the builder to give written notice before work starts requiring the owner to satisfy the builder that the owner has title to the land and, by production of evidence in writing, that the owner can pay the contract price.
If the owner fails to satisfy the builder within 10 working days of receiving that notice, section 15(3)(c) protects a clause letting the builder terminate the contract or the variation by written notice given within a further 10 working days.
Read that precisely. The Act does not confer the right. It shelters a contract clause that confers it. A WA builder whose contract lacks the clause has no such exit.
Notice to remedy and the repudiation trap
This is where WA builders lose. A contractual right to terminate for owner default almost always runs through a notice to remedy that specifies the default, allows a stated period to fix it and states the consequence of not fixing it.
Skip that step, shorten it or issue it for a default that has not happened, and there is no valid termination. There is an unjustified purported termination, and that is itself repudiation. The builder who gets the notice wrong hands the owner the right to accept the repudiation and sue for the cost of finishing with someone else.
Section 29(2) keeps the common law live: the Act does not limit or derogate from any civil remedy at law or in equity.
What the builder can recover
Where a contract is terminated under section 4(5), 10(4) or 14(3) or Schedule 1, section 20 lets either party complain to the Building Commissioner for an adjustment of rights. The builder can claim for materials supplied, for home building work or other services performed and for costs incurred, and the Act expressly names overhead expenses and loss of profit.
Schedule 1 clause 4(c) adds a narrower entitlement. Where the owner terminates because a permitted price increase exceeded 5 per cent of the contract price, the owner must compensate the builder for reasonable costs incurred up to termination.
Escalation to the State Administrative Tribunal
Termination disputes start with the Building Commissioner at Building and Energy, which lists termination payments among the home building work contract matters carrying a limit of generally three years from when the contract was entered into or from when the cause of dispute arose. A notice of proposed complaint must reach the other party at least 14 days before lodgement.
The Building Commissioner can refer or transfer the matter to the State Administrative Tribunal. An application to review a decision of the Building Commissioner must be made within 28 days.
Where Home Indemnity Insurance stops
Home indemnity insurance responds only where a relevant circumstance exists in relation to the builder. Building and Energy states those as an individual builder who dies, disappears or becomes insolvent, a corporate builder that ceases to exist or becomes insolvent, and a builder whose registration is cancelled or not renewed for failing the prescribed financial requirements.
A solvent, registered builder who simply walks off site is none of those things. The owner has no home indemnity insurance claim at all. They have a contract claim against a builder that is still trading, and they have to run it themselves. That gap is the sharpest practical fact in WA termination.
Citations
- [1]
Home Building Contracts Act 1991 (WA)
legislationParliamentary Counsel's Office, Western Australia · WA · accessed 16/07/2026
Section 15(3)(c): if the owner fails to satisfy the builder within 10 working days of receipt of a notice, the builder may terminate the contract or the variation by notice in writing given within a further 10 working days. Section 20 permits claims including overhead expenses and loss of profit.
- [2]
governmentBuilding and Energy, Government of Western Australia · WA · accessed 16/07/2026
For specific home building work contract matters (contract variations, breach of contract, termination payments) the time limit for making a complaint is generally three years from when the contract was entered into or from when the cause of dispute arose.
- [3]
Building and Construction, State Administrative Tribunal
governmentState Administrative Tribunal of Western Australia · WA · accessed 16/07/2026
The Building Commissioner can refer or transfer matters to SAT. Applications for review must be made within 28 days of the decision that is sought to be reviewed.
- [4]
Home indemnity insurance fact sheet
governmentBuilding and Energy, Department of Local Government, Industry Regulation and Safety · WA · accessed 16/07/2026
A relevant circumstance can occur if the builder is an individual and the builder dies, disappears or becomes insolvent; or the builder is not an individual and ceases to exist or becomes insolvent; or registration is cancelled or not renewed for failing prescribed financial requirements.
- [5]
Home Building Contracts Regulations 1992 (WA)
legislationParliamentary Counsel's Office, Western Australia · WA · accessed 16/07/2026
Schedule 1 Notice for the Home Owner: to terminate you must give notice in writing to the builder before the building work is finished. If a contract is terminated you may make a complaint to the Building Commissioner claiming financial adjustments.
How this was researched
This entry was drafted from primary Australian sources (legislation, regulator publications and industry guidance) and reviewed and signed off by Hunter Jacobs, Director, TradeForm. Citations link to the source documents you can verify yourself. The entry is re-verified on a cadence and automatically flagged for review when a watched source changes.
Disclaimer
This is general information about Australian construction and business topics. It is not legal, engineering, or financial advice. Laws and standards change. Verify current requirements with a licensed professional in your jurisdiction before relying on this content.