When a Tasmanian Builder Can Lawfully Terminate a Building Contract
Tasmania's 2016 Act gives a builder no statutory right to terminate. The grounds live in the contract and the common law, and skipping the show-cause step turns termination into repudiation.
What it is
Walking off a Tasmanian job is the most expensive decision a builder can make. Get the grounds or the procedure wrong and the termination is itself a breach, the owner accepts it as repudiation and the builder pays for someone else to finish the house.
The first thing to establish is what the statute gives you. For Tasmania, nothing.
The Act is silent on termination grounds
The Residential Building Work Contracts and Dispute Resolution Act 2016 (Tas) creates no statutory right for a builder to terminate. The word termination appears once in the operative Act, at section 63, and only to confirm that terminating a contract does not strip TASCAT of jurisdiction over what happened beforehand.
That silence is the point. It is not universal. Victoria gives a builder a statutory termination right at section 49X of its Domestic Building Contracts Act 1995. Tasmania has no equivalent. Neither do most states. A Tasmanian builder who terminates is exercising a contractual right or a common law right, never a statutory one.
So the contract has to carry it
Because the Act is silent, the Director of Building Control's Determination on Mandatory Contract Provisions fills the space. It requires every residential building work contract to state the circumstances in which the contract can be terminated by either party. It separately requires the contract to state the remedies for breach and lists termination as one of them.
A contract vague about termination is not merely risky drafting. It fails a mandatory contract provision.
Follow your own procedure exactly
Most contracts require a notice to remedy or show cause: a written notice specifying the default, giving a period to fix it and only then permitting termination if the default continues. That step is contractual rather than statutory, which tempts builders to treat it as optional. It is not.
Terminating without the notice, before the remedy period expires or on a ground the contract does not list means the builder has purported to end a contract it had no right to end. That is a repudiation. The owner may accept it and sue for the cost of completion above the contract price plus delay losses.
Repudiation cuts both ways. An owner who refuses access, refuses to pay a valid claim or makes clear they will not perform may repudiate, giving the builder a right to accept and terminate. The bar is high. An honest mistake about contractual rights is usually not enough.
What the builder can recover
On a valid termination the builder recovers what the contract provides, typically the value of work performed and unpaid plus damages for loss of bargain. Section 62(7) tells TASCAT to take into account the reasonable price or cost of the work and the price specified in the contract, so an inflated final claim will not survive scrutiny.
A harsh termination clause is not a safe harbour either. Section 62(2) lets TASCAT declare a term unjust, declare it void or vary it, weighing factors in section 62(5) including whether the builder knew the term would cause the owner undue hardship. Section 78 voids any arrangement that defeats or evades the Act.
The dispute pathway
Either party may lodge a notice of dispute with the Director of Building Control. Section 47(1A) requires it within 6 years after the date of practical completion, or within 6 years of the work being performed if there is no such date. CBOS requires a genuine attempt to resolve the matter first and bars the notice if court action is on foot.
The Director accepts or rejects within 10 business days, then establishes a mediation panel within 2 business days. Section 54 allows 20 business days from that point. Mediation is voluntary. If it fails, TASCAT determines the matter in the Civil and Consumer stream, with power under section 62(2) to order money, damages, rectification or completion. Section 65 lets the Supreme Court or the Magistrates Court refer proceedings to TASCAT. Section 46(1) preserves the right to go to court instead.
Why the stakes are higher in Tasmania
Tasmania has no compulsory home warranty insurance. It was abolished in 2008. The Residential Building (Home Warranty Insurance Amendments) Act 2023 commences on a day to be proclaimed that has not arrived. No insurer stands behind a wrongful termination. The contract and the statutory dispute pathway are the owner's only protection, which is why TASCAT looks hard at whether the builder followed its own clause.
Citations
- [1]
Residential Building Work Contracts and Dispute Resolution Act 2016 (Tas), ss 47, 48, 49 and 63
legislationTasmanian Government · TAS · accessed 17/07/2026
Section 63: for the avoidance of doubt, the termination of a residential building work contract does not affect the jurisdiction of TASCAT under this Part in respect of a matter that occurred under the contract before it was terminated. The Act contains no builder termination right.
- [2]
Director's Determination: Mandatory Contract Provisions
governmentConsumer, Building and Occupational Services (Tas) · TAS · accessed 17/07/2026
Termination: the contract must state the circumstances in which the contract can be terminated by either party. Remedies for breach: the contract must clearly state the remedies available to either party if there is breach of the contract, which may include termination of contract.
- [3]
legislationTasmanian Government · TAS · accessed 17/07/2026
Section 62(2) lets the Tribunal order money, damages, rectification or completion, declare a term unjust or void, or vary it. Section 62(7) directs the Tribunal to the reasonable price or cost of the work. Section 65 allows the Supreme Court or Magistrates Court to refer proceedings to the Tribunal.
- [4]
Mediation of residential building disputes
governmentConsumer, Building and Occupational Services (Tas) · TAS · accessed 17/07/2026
Mediation services can be arranged by the Director of Building Control. Before applying you must have first attempted to resolve the matter with the other party. If you are engaged in other adjudication, arbitration or court action you are not able to apply. Attending mediation is voluntary.
- [5]
Residential Building (Home Warranty Insurance Amendments) Act 2023 (Tas), s 2
legislationTasmanian Government · TAS · accessed 17/07/2026
Section 2 Commencement: the provisions of this Act commence on a day or days to be proclaimed. The Act is published as made and has no in-force version.
How this was researched
This entry was drafted from primary Australian sources (legislation, regulator publications and industry guidance) and reviewed and signed off by Hunter Jacobs, Director, TradeForm. Citations link to the source documents you can verify yourself. The entry is re-verified on a cadence and automatically flagged for review when a watched source changes.
Disclaimer
This is general information about Australian construction and business topics. It is not legal, engineering, or financial advice. Laws and standards change. Verify current requirements with a licensed professional in your jurisdiction before relying on this content.