Skip to content
VICContractsVerified 18 July 2026

Contract Termination Rights for Builders in Victoria

Section 49X of the Domestic Building Contracts Act 1995 (Vic) gives a Victorian builder a statutory right to end a domestic building contract once the owner breaches a dispute resolution order.

What it is

Victoria is unusual here. Most Australian home building statutes leave a builder right to walk away to the contract plus the common law. The Domestic Building Contracts Act 1995 (Vic) does not. Section 49X gives a Victorian builder a statutory right to end a domestic building contract. Section 67A gives it a VCAT remedy afterwards.

That right is narrow. It is not a general escape hatch for a builder who wants off a bad job.

The statutory route: section 49X

Section 49X sits inside the dispute resolution order machinery in Part 4 Division 6. The sequence runs like this. A domestic building work dispute goes to the Building and Plumbing Commission. Conciliation fails, or the record of agreement is breached. The chief dispute resolution officer issues a dispute resolution order. The owner breaches it. A breach of dispute resolution order notice is served under section 49U(2) against the owner.

Only then does section 49X open. The builder may end the contract by written notice to the chief dispute resolution officer and the building owner, provided:

  • a breach notice has been served under section 49U(2) for a failure by the building owner
  • either the owner window to seek VCAT review of the decision to issue that notice has closed without an application, or the owner applied and the decision was affirmed
  • the builder has complied with any dispute resolution order issued to the builder in that dispute, to the extent possible in the circumstances
  • the builder has complied with any conditions it had to satisfy before the owner obligation to comply arose

Section 49X(2) then does the important thing: once the builder ends the contract this way, the builder is released from any further performance.

Those last two conditions are the trap. A builder sitting on its own unsatisfied order cannot use section 49X to escape.

What the builder recovers

Section 67A. Where a builder ends a contract in accordance with Division 6 of Part 4, it may apply to VCAT for an order against the building owner. VCAT may make any order it considers fair, including ordering the owner to pay for work performed under the contract plus damages for loss of work resulting from the ending of the contract.

The Building and Plumbing Commission puts the same entitlement plainly. Where an owner fails to comply with a dispute resolution order, the builder is entitled to end the contract and apply to VCAT for payment for work already carried out, damages for the loss of work caused by the early end, plus any other appropriate orders.

The contractual route and why skipping notice is fatal

Most terminations never touch section 49X. They run off the contract default clause: notice of breach, a period to remedy, termination if the breach continues.

Skipping that procedure is what converts a termination into a repudiation. A builder who downs tools and fires off a termination notice without first giving the contractual notice to remedy has not exercised a right. It has committed the breach. The owner accepts the repudiation. The builder then defends a claim for the cost of completion instead of recovering for work done.

Repudiation cuts both ways. An owner who refuses site access, refuses to pay a properly claimed stage payment or directs the builder to stop indefinitely may repudiate, giving the builder a common law right to accept and terminate. That right runs independently of section 49X. It carries its own risk: a tribunal may disagree that the conduct was repudiatory at all.

The conciliation gate in front of VCAT

Victoria puts a gate before the tribunal. Section 56 says a party to a domestic building work dispute must not apply to VCAT unless the chief dispute resolution officer has issued a certificate of conciliation stating the dispute was not suitable for conciliation, or was not resolved by it. The application must carry a copy of that certificate. The only carve-out in section 56(3) is a proceeding for an order in the nature of an injunction.

So a Victorian builder cannot terminate on Monday and issue at VCAT on Tuesday. The dispute goes to the BPC first.

The cost of getting it wrong

One BPC rule deserves its own line. If a builder issued with a breach notice challenges it at VCAT, the owner must wait for the review outcome before exercising their right to end the contract. The mirror sits in section 49X(1)(b): the owner review window must close, or the decision must be affirmed, before the builder right crystallises. Ending the contract before that point is a wrongful termination dressed up as a statutory one.

Wrongful termination is expensive. The builder loses the section 67A pathway. It loses the section 49X(2) release from further performance. It faces the owner claim for the cost to complete, with no statutory shelter left.

Citations

  1. [1]

    Domestic Building Contracts Act 1995 (Vic)

    legislationVictorian Government · VIC · accessed 16/07/2026

    Section 49X(1): a builder may, by written notice to the chief dispute resolution officer and the building owner, end a domestic building contract that is the subject of a dispute resolution order if a breach of dispute resolution order notice has been served under section 49U(2) in relation to a failure by the building owner and the review period has ended or the decision affirmed, and the builder has complied with any dispute resolution order issued to the builder. Section 49X(2): the builder is released from any further performance. Section 67A(4): VCAT may order the building owner to pay for work performed and damages for loss of work.

  2. [2]

    Binding orders

    governmentBuilding and Plumbing Commission · VIC · accessed 16/07/2026

    The builder is then entitled to end the contract and apply to VCAT for payment for work already carried out under the contract, an order for damages as a result of the loss of work caused by the early end to the contract, any other appropriate orders. If a builder challenges the breach notice, the owner must wait for the outcome of the review in VCAT before exercising their right to end the contract.

  3. [3]

    Conciliation outcomes

    governmentBuilding and Plumbing Commission · VIC · accessed 16/07/2026

    Where a dispute resolution order is not appropriate, we will issue a certificate of conciliation stating that the dispute was not resolved by conciliation. This will enable either party to make an application to VCAT.

  4. [4]

    When you can apply to VCAT

    governmentBuilding and Plumbing Commission · VIC · accessed 16/07/2026

    A party required to comply with a dispute resolution order may seek review of the order in VCAT if the description of the defective or incomplete building work is not accurate, the due date is not reasonable, or any requirement to take specific action is not reasonable. A party that applies to VCAT for review and is unsuccessful may have costs awarded against them.

  5. [5]

    Building and construction disputes

    governmentVictorian Civil and Administrative Tribunal · VIC · accessed 16/07/2026

    Domestic or commercial building disputes between a property owner, builder, sub-contractor, architect, engineer or other building practitioner. Cases requiring more than a one day hearing will not be allocated a final hearing date until all interlocutory steps are complete.


How this was researched

This entry was drafted from primary Australian sources (legislation, regulator publications and industry guidance) and reviewed and signed off by Hunter Jacobs, Director, TradeForm. Citations link to the source documents you can verify yourself. The entry is re-verified on a cadence and automatically flagged for review when a watched source changes.

Disclaimer

This is general information about Australian construction and business topics. It is not legal, engineering, or financial advice. Laws and standards change. Verify current requirements with a licensed professional in your jurisdiction before relying on this content.