Security of Payment WA: The 2021 Act and New Adjudication Regime
The Building and Construction Industry (Security of Payment) Act 2021 (WA) replaced the Construction Contracts Act 2004 from 1 February 2022 and brought Western Australia into line with the East
What it is
The Building and Construction Industry (Security of Payment) Act 2021 (WA) is the current statute governing progress payments and adjudication for construction work in Western Australia. It replaced the older Construction Contracts Act 2004 (WA) in three staged phases starting 1 February 2022, and the rollout was complete across all contracts by 1 February 2024.
The new Act is closer to the East Coast model used in NSW and Victoria. That is a significant change. The 2004 regime required the claimant to wait for a payment dispute to crystallise before applying for adjudication. The 2021 Act front-loads the timeline with a statutory payment claim, a payment schedule and tight default deadlines.
Who it applies to
The Act applies to construction contracts for construction work or related goods and services carried out in WA. It covers head contractors, subcontractors, suppliers and consultants on residential, commercial and civil projects.
There is an owner-occupier carve-out. Section 9 excludes construction contracts for the construction of a single dwelling-house, or for renovating, altering, extending, repairing or restoring a single dwelling-house, where the contract is between the head contractor and the resident owner. The Act still applies down the chain between the head contractor and its subbies and suppliers.
Payment claims
Under section 24 a payment claim must:
- be in writing
- identify the work and the contract
- state the claimed amount
- state that it is made under the Act
The claim can be served at the times set by the contract. If the contract is silent the default reference period is monthly.
A head contractor must also lodge a head contractor declaration confirming that subcontractors have been paid amounts due. False declarations are an offence.
Payment schedule and default deadlines
A respondent has 15 business days to give a payment schedule under section 25, or a shorter period if the contract specifies one. The schedule must:
- identify the payment claim
- state the scheduled amount
- give reasons for withholding any amount
If the respondent does not give a schedule within the statutory period it becomes liable for the full claimed amount on the due date. The claimant can recover the amount in court or apply for adjudication.
Note that the WA scheme uses a longer default schedule period than NSW or Victoria. Check the contract carefully because parties can shorten the deadline but not extend it past the statutory maximum.
Adjudication
Adjudication applications under section 26 must be made within 20 business days of the scheduled amount being due, or of the date the respondent missed the schedule. The application is lodged with an authorised nominating authority. The adjudicator must determine the application within 10 business days of acceptance, subject to extensions.
The State Administrative Tribunal hears reviews of adjudication decisions on limited grounds, in line with the previous WA regime. Determinations are otherwise enforceable as judgment debts.
Retention trust scheme
The 2021 Act introduced a Project Bank Account-style retention trust scheme. Head contractors holding retention money from subcontractors must hold it in a designated retention money trust account. This is a WA-specific feature aimed at protecting subbies if the head contractor becomes insolvent.
What this means for TradeLens compliance
WA builders need to retrain anyone trained on the old Construction Contracts Act regime. Reference dates, payment-schedule deadlines and adjudication windows are all different. The retention trust scheme also creates new financial control obligations that intersect with progress claim cycles. A simple monthly cadence with calendared statutory deadlines is the safest baseline.
Citations
- [1]
Building and Construction Industry (Security of Payment) Act 2021 (WA)
legislationWA Government · WA · accessed 27/05/2026
An Act about security of payment for construction work and related goods and services in Western Australia.
- [2]
Section 24 Payment Claims, SOP Act 2021 (WA)
legislationWA Government · WA · accessed 27/05/2026
A payment claim must identify the work, state the amount claimed and state that it is made under the Act.
- [3]
Section 25 Payment Schedules, SOP Act 2021 (WA)
legislationWA Government · WA · accessed 27/05/2026
A respondent may respond to a payment claim by giving a payment schedule within 15 business days.
- [4]
Section 26 Adjudication Applications, SOP Act 2021 (WA)
legislationWA Government · WA · accessed 27/05/2026
A claimant may apply for adjudication of a payment dispute within 20 business days.
- [5]
governmentWA Department of Mines, Industry Regulation and Safety · WA · accessed 27/05/2026
Information on the new Security of Payment Act 2021 including payment claims, adjudication and the retention trust scheme.
How this was researched
This entry was drafted from primary Australian sources (legislation, regulator publications and industry guidance) and reviewed and signed off by Oli Rossi, Subject-matter expert, TradeForm Knowledge. Citations link to the source documents you can verify yourself. The entry is re-verified on a cadence and automatically flagged for review when a watched source changes.
Disclaimer
This is general information about Australian construction and business topics. It is not legal, engineering, or financial advice. Laws and standards change. Verify current requirements with a licensed professional in your jurisdiction before relying on this content.