Skip to content
WAContractsVerified 18 July 2026

Progress Payment Rules Under the HBCA in Western Australia

Section 10(1)(b) of the HBCA 1991 allows only genuine progress payments for work already performed or materials already supplied. Nothing before commencement except the 6.5 per cent deposit.

What it is

Section 10 of the Home Building Contracts Act 1991 (WA) is one section doing two jobs. Section 10(1)(a) governs what a builder can take before work starts. Section 10(1)(b) governs everything after.

The rule after commencement is short. A builder must not enter a contract entitling the builder to demand or receive any payment unless the payment is a genuine progress payment for work already performed or materials or services already supplied, or is of a prescribed kind. The penalty is $10,000.

Nothing upfront but the deposit

Before commencement, section 10(1)(a) permits only a deposit of not more than 6.5 per cent of the total amount payable, or a payment of a prescribed kind. The only prescribed kind is regulation 3A, which lifts the deposit to 20 per cent for qualifying off-site cabinetry work.

That means there is no lawful mobilisation payment, no lawful pre-order allowance and no lawful deposit-plus-materials structure. Building and Energy puts the test in physical terms: a builder cannot ask for a progress payment for the purchase and delivery of bricks until the bricks have actually been delivered to the site. The regulator adds that upfront payments beyond the deposit can affect any claim the owner later makes under a home indemnity insurance policy, which generally does not cover money paid in advance.

The word doing the work is "already"

Section 10(1)(b)(i) is written in the past tense on purpose. A genuine progress payment is for work already performed or materials or services already supplied. A claim tied to a date, a percentage of elapsed programme or an anticipated stage is not a genuine progress payment no matter what the schedule calls it.

Section 10(5) then closes the loop on conduct as well as drafting. A builder must not demand or receive any payment after commencement unless it is a genuine progress payment or of a prescribed kind, again with a $10,000 penalty. So a compliant contract wrongly claimed against is still an offence.

Two things that help the builder

Prefabricated and transportable dwellings. Section 10(2) deems a payment for materials or a dwelling in prefabricated or transportable form to be a genuine progress payment, but only if property in the materials or dwelling passes absolutely to the owner on payment. It applies even though the materials are not yet placed on or affixed to the owner's land. Absolutely is the operative word: a retention of title clause defeats the deeming and the payment reverts to being an unlawful advance.

The schedule presumption. Section 10(3) provides that where a contract sets out a schedule of payments due at specified stages, and a payment is demanded in accordance with that schedule, the payment is taken to be a genuine progress payment until the contrary is shown. That is a rebuttable presumption, not a safe harbour. It shifts the onus to the owner. It does not make a front-loaded schedule lawful, because an owner who shows the money outruns the work displaces it.

What a non-compliant schedule actually costs

Not the contract. Section 27(1) provides that a contract or a provision is not illegal, void or unenforceable only because a requirement of the Act is not complied with. A builder should not read that as comfort, because the consequences that do apply are the ones that hurt.

  • Termination. Section 10(4) gives the owner a right to terminate under section 19 where the builder entered the contract in breach of section 10(1). The right crystallises at signing, before any money moves.
  • Penalties. $10,000 under section 10(1) and again under section 10(5). Both are prescribed offences under regulation 8 of the Home Building Contracts Regulations 1992, each carrying a modified penalty of $1,000 on an infringement notice.
  • Orders that the money is not payable. Section 17 routes a Part 2 breach to a complaint under the Building Services (Complaint Resolution and Administration) Act 2011. Section 41(2)(e) of that Act empowers an order declaring that a specified amount of money claimed, or money claimed for specified work, is not payable. Section 41(2)(c) allows an order that an amount already paid be repaid.

That third limb is the real exposure. The contract survives, and the claim does not.

The band, and what sits outside it

Section 10 only reaches a home building work contract as defined in section 3(1), and regulation 2A prescribes the band at more than $7,500 and less than $500,000. Above $500,000 there is no statutory progress payment rule at all, and the contract carries the whole load. Cost plus contracts are excluded from the definition, so section 10 does not touch them either.

Progress payments are on the table in the current review of WA's home building contract laws, with recommendations due in September 2026.

Citations

  1. [1]

    Home Building Contracts Act 1991 (WA), sections 10, 17 and 27

    legislationParliamentary Counsel's Office (WA) · WA · accessed 16/07/2026

    Section 10(1)(b) permits a payment after commencement only if it is a genuine progress payment for work already performed or materials or services already supplied, or is of a prescribed kind. Penalty: $10,000. Section 10(2) deems prefabricated materials payments genuine if property passes absolutely. Section 10(3) presumes scheduled stage payments genuine until the contrary is shown. Section 10(4) allows termination under section 19. Section 10(5) prohibits demanding or receiving a non-genuine payment.

  2. [2]

    Home Building Contracts Regulations 1992 (WA), regulations 2A, 3A and 8

    legislationParliamentary Counsel's Office (WA) · WA · accessed 16/07/2026

    Regulation 2A prescribes $7,500 and $500,000 for the definition of home building work contract. Regulation 3A prescribes the 20% cabinetry deposit for section 10(1)(a)(ii). Regulation 8 prescribes modified penalties of $1,000 for offences against sections 10(1) and 10(5).

  3. [3]

    Building or renovating your home

    governmentBuilding and Energy, Government of Western Australia · WA · accessed 16/07/2026

    Once work has started, you should only make progress payments for work that has actually been done or for materials have already been supplied. For example, your builder cannot ask for a progress payment for the purchase and delivery of bricks until the bricks have actually been delivered to the site. With the exception of the deposit, upfront payments to your contract are not allowed and, if made, can affect any claim you may have under your home indemnity insurance policy.

  4. [4]

    Building Services (Complaint Resolution and Administration) Act 2011 (WA), section 41

    legislationParliamentary Counsel's Office (WA) · WA · accessed 16/07/2026

    A HBWC remedy order may include an order that a person pay a specified amount payable under the contract, an order declaring that a specified amount is not payable to a person under the contract and, if already paid, an order that the builder or owner repay that amount, and an order declaring that a specified amount of money claimed or money claimed for specified work is not payable by a person.

  5. [5]

    Review of Western Australia's home building contract laws

    governmentBuilding and Energy, Government of Western Australia · WA · accessed 16/07/2026

    Key topics for consideration during the review include price increases and progress payments. Final recommendations report to be provided to government for consideration September 2026.


How this was researched

This entry was drafted from primary Australian sources (legislation, regulator publications and industry guidance) and reviewed and signed off by Hunter Jacobs, Director, TradeForm. Citations link to the source documents you can verify yourself. The entry is re-verified on a cadence and automatically flagged for review when a watched source changes.

Disclaimer

This is general information about Australian construction and business topics. It is not legal, engineering, or financial advice. Laws and standards change. Verify current requirements with a licensed professional in your jurisdiction before relying on this content.