Qualified Supervisor Requirements for NSW Building Contractors
A NSW company or partnership contractor licence must have at least one qualified supervisor. Losing the supervisor without a replacement suspends operational capacity.
What it is
A New South Wales contractor licence held by a company or partnership requires at least one qualified supervisor at all times. The qualified supervisor is the person on the licence responsible for the technical work and for ensuring compliance with the Home Building Act 1989 (NSW) and the Home Building Regulation 2014 (NSW).
Section 25 of the HBA and the regulations govern the qualified supervisor requirement. Losing the supervisor without a replacement effectively suspends the company's operational capacity because the licence cannot be exercised without the qualified supervisor endorsement.
The qualified supervisor role
A qualified supervisor holds a supervisor certificate in the same or a broader work class as the contractor licence. The supervisor certifies that they are personally responsible for the day-to-day technical direction of the work.
Building Commission NSW issues qualified supervisor certificates on similar qualification and experience criteria to contractor licences. The supervisor must have the practical building competencies and pass the character and probity assessment.
Company or partnership contractor licences
Where the contractor licence is held by a company, the company itself is the licensee. But the company cannot personally carry out or supervise the work. The qualified supervisor is the natural person on the licence who does.
Section 25 requires the supervisor to be nominated on the licence and to actually supervise the work. A qualified supervisor listed on the licence but not actually involved in the work is grounds for licence action against the company.
The one supervisor per licence rule
A qualified supervisor can be nominated on more than one contractor licence, but Building Commission NSW guidance limits this to a small number in practice. A supervisor spread too thinly across multiple licences cannot genuinely supervise each project and risks losing the certificate.
The practical rule is that a company should have its own dedicated supervisor. Shared supervisors work only in specific structures (sister companies, group entities) and require clear evidence of actual supervision.
What happens when the supervisor leaves
Where the qualified supervisor leaves the company or ceases to hold the certificate, the contractor licence is at risk. Section 25(2) requires the licensee to notify Building Commission NSW within 7 days of any change to the qualified supervisor.
If no replacement supervisor is nominated, Building Commission NSW can suspend the licence or impose conditions requiring a replacement within a defined period. In practice, the company must have a replacement supervisor nominated before or immediately after the outgoing supervisor's departure.
Sole trader contractor licences
For a sole trader contractor licence, the individual is both the licensee and the supervisor. That simplifies the supervisor question but does not remove it: the sole trader must hold the appropriate supervisor certification for the work class.
Consequences of unsupervised work
Building work carried out by a company or partnership contractor without a nominated qualified supervisor exposes the company to:
- offence proceedings under section 25 of the HBA
- licence conditions, suspension or cancellation by Building Commission NSW
- possible contract enforceability issues under section 10
Owners contracting with a NSW company builder should verify the qualified supervisor's identity and appropriate class through the HBC Check portal before signing.
How NSW compares
NSW's qualified supervisor framework aligns with QLD's Nominated Supervisor requirement under Schedule 1A of the QBCC Act 1991 and with WA's Nominated Supervisor under the Building Services (Registration) Act 2011. VIC uses a comparable framework under the Building Act 1993 (Vic) domestic builder (manager) class.
The distinctive NSW feature is the section 25(2) 7-day notification requirement for supervisor changes, which is shorter than most states.
Citations
- [1]
Home Building Act 1989 (NSW), section 25
legislationNSW Government · NSW · accessed 17/07/2026
Section 25 qualified supervisor requirement for company and partnership contractor licences. Section 25(2) 7-day notification of change requirement.
- [2]
Qualified supervisor certificates
governmentNSW Government · NSW · accessed 17/07/2026
Building Commission NSW guidance on qualified supervisor certificates: eligibility, work classes, application process, notification requirements.
- [3]
QBCC Act 1991 (Qld), Schedule 1A and Building Services (Registration) Act 2011 (WA)
legislationQueensland Government · QLD · accessed 17/07/2026
QBCC Nominated Supervisor framework under Schedule 1A. WA Nominated Supervisor framework under the Building Services (Registration) Act 2011. Comparative context for NSW section 25.
How this was researched
This entry was drafted from primary Australian sources (legislation, regulator publications and industry guidance) and reviewed and signed off by Hunter Jacobs, Director, TradeForm. Citations link to the source documents you can verify yourself. The entry is re-verified on a cadence and automatically flagged for review when a watched source changes.
Disclaimer
This is general information about Australian construction and business topics. It is not legal, engineering, or financial advice. Laws and standards change. Verify current requirements with a licensed professional in your jurisdiction before relying on this content.