Final Payment and Retention Release on Residential Builds (AU)
How the final claim works at Practical Completion, what triggers retention release at the end of the DLP, and what a defects notice does to your money.
What it is
The final payment on a residential build is the last money owed to the builder. It moves in two parts. The first part is the final claim made when the works reach Practical Completion (PC). The second part is the retention or final hold that releases at the end of the Defects Liability Period (DLP).
These two moments are different events with different legal triggers. Treat them as one and you will either overpay or under-secure.
Practical Completion
Practical Completion is the point at which the works are complete except for minor defects or minor omissions that do not prevent the home from being used for its intended purpose. The standard residential contracts (HIA, Master Builders and the Fair Trading template contracts in each state) all use this language with small variations.
What PC actually triggers
When PC is reached, several clocks start at once.
The builder issues a Notice of Practical Completion. The owner has a short period (commonly 5 to 10 business days) to either accept PC or dispute it and list the items they say must be finished first.
The risk in the works passes from the builder to the owner. The owner takes out their own building insurance from this date.
The Defects Liability Period starts running. This is usually 13 weeks (3 months) under HIA contracts or 6 months under most Master Builders forms, and can be longer for some inclusions like waterproofing.
The final claim becomes due. The contract sets the payment period (typically 5 working days from delivery of the claim plus the keys).
Disputed PC
If the owner disputes PC, the contract usually requires them to give a written list of items. The builder either finishes those items and re-issues the notice, or refers the dispute to the contract's dispute clause. In most state regimes the dispute then runs through the consumer tribunal pathway.
The final claim
The final claim is the last progress claim. It captures the final stage value plus any approved variations not yet claimed. Two things sit between the claim and a clean payment.
Defects notice impact
If the owner serves a defects notice during the PC period, the builder must rectify before the final claim becomes payable. Most contracts allow the owner to withhold an amount reasonably required to fix the listed defects. That amount is not the whole claim. It is a set-off against the cost of rectification.
This is where disputes get sharp. The owner often wants to withhold the full final claim. The contract usually only allows withholding the rectification value plus a reasonable margin.
Set-off and counterclaim
Where the owner has a genuine claim for delay damages, defective work or unfinished items, they can set those amounts off against the final payment. The set-off must be quantified and notified in writing. A general claim that "the work is not good enough" is not a set-off.
Statutory carve-outs
In NSW the Home Building Act 1989 section 8A controls the form of progress payments on residential work, but the final payment mechanism is largely contract-driven. The Security of Payment Act does not apply between builder and owner-occupier, so the final claim does not get adjudicated under SoP. It is resolved through the contract and NCAT.
Retention and the DLP
The retention amount is the portion of the contract price held back to secure rectification of defects that emerge after PC. Two patterns are common in residential work.
Retention pattern
The owner holds 5 per cent of each progress payment, with half released at PC and the balance released at the end of the DLP. Net effect is 2.5 per cent held through the DLP.
Bank guarantee pattern
The builder gives a bank guarantee instead of cash retention. The guarantee is returned at the end of the DLP if no claims are on foot.
In Queensland, the QBCC requirement is that if a contract does not specify a DLP then any retention or security must be released 12 months after Practical Completion, and it is an offence to withhold retention without reasonable excuse.
Release at the end of the DLP
At the end of the DLP, the builder gives a Notice of End of Defects Liability Period. In Queensland this is the QBCC Form S67NC, served at least 10 business days before the DLP ends. The notice tells the owner the amount of retention proposed to be released and gives them a chance to raise any final defects.
If the owner does not respond, the retention is released. If the owner raises defects, the builder either fixes them and then takes the retention, or the dispute heads to the tribunal.
State variations to watch
Final payment mechanisms vary by state in small ways that matter.
NSW
Home Building Act 1989 section 8A controls progress payments. The final claim is governed by the contract. NCAT handles disputes up to its limit.
Victoria
Domestic Building Contracts Act 1995 controls the contract structure. Section 40 limits progress payments to work already carried out. DBDRV runs conciliation before VCAT.
Queensland
The QBCC defects liability framework under the Domestic Building Contracts schedule of the QBCC Act controls residential DLPs. Form S67NC is the trigger document for retention release. Common DLP is 12 months for residential.
WA and SA
Each has its own building services framework. Retention release timing is contract-driven, with the SAT (WA) or SACAT (SA) handling disputes.
How to run a clean final payment
A few practical habits keep this stage out of court.
Walk the site with the owner at PC. List items together. Sign the list.
Photograph the home at PC. The state of finishes at PC sets the baseline for any later defect claim.
Issue the final claim with the PC notice. Attach the variation schedule and any reconciliation against the original contract sum.
Diary the DLP end date. Send the end-of-DLP notice in the time the contract requires.
Get the retention release in writing. A signed release closes the contract.
Citations
- [1]
Home Building Act 1989 (NSW) section 8A
legislationAustLII · NSW · accessed 28/05/2026
Authorised progress payments under residential building contracts above the prescribed amount.
- [2]
Domestic Building Contracts Act 1995 (Vic) section 40
legislationAustLII · VIC · accessed 28/05/2026
A builder under a major domestic building contract must not demand or receive a progress payment unless the payment is for work the builder has carried out under the contract.
- [3]
governmentQueensland Building and Construction Commission · QLD · accessed 28/05/2026
If a building contract does not specify a defects liability period then any retention amounts or security held must be released 12 months after practical completion.
- [4]
Form S67NC Notice of End of Defects Liability Period
governmentQueensland Building and Construction Commission · QLD · accessed 28/05/2026
Notice must be provided to the contracted party within 10 business days before the end of the defects liability period.
- [5]
Domestic Building Dispute Resolution Victoria
governmentConsumer Affairs Victoria · VIC · accessed 28/05/2026
DBDRV conciliates domestic building disputes between owners and builders before VCAT proceedings.
- [6]
Domestic Building Contracts Act 1995 (Vic) section 11 deposit limit
legislationAustLII · VIC · accessed 28/05/2026
The maximum deposit is 10 per cent if the contract price is less than 20,000 dollars or 5 per cent if the price is 20,000 dollars or more.
How this was researched
This entry was drafted from primary Australian sources (legislation, regulator publications and industry guidance) and reviewed and signed off by Hunter Jacobs, Director, TradeForm. Citations link to the source documents you can verify yourself. The entry is re-verified on a cadence and automatically flagged for review when a watched source changes.
Disclaimer
This is general information about Australian construction and business topics. It is not legal, engineering, or financial advice. Laws and standards change. Verify current requirements with a licensed professional in your jurisdiction before relying on this content.