Building Work Contract Requirements in SA
SA domestic building work contracts must be written at $20,000 or more, carry the section 28 particulars plus a Form 1 notice and sit behind $250,000 indemnity cover in place before work starts.
What it is
In South Australia a residential building contract is called a domestic building work contract. The Building Work Contractors Act 1995 (SA) and the Building Work Contractors Regulations 2011 set the rules, and Consumer and Business Services (CBS) enforces them.
Part 5 of the Act does three separate jobs. Division 1 says what the contract must contain. Division 2 implies warranties into it whatever it says. Division 3 forces insurance in front of it before the builder starts.
The trigger for Division 1 is value, and that value moved on 10 November 2025.
The $20,000 trigger
Division 1 does not apply to minor domestic building work (s27(2)). Section 3(1) defines minor domestic building work as work at a cost to the building owner that is less than the sum prescribed by regulation. Regulation 4 prescribes $20,000.
So the rule is: at $20,000 or more the section 28 formalities bite. Below $20,000 nothing in Division 1 applies.
Watch the boundary. It is $20,000 or more, not over $20,000. A job priced at exactly $20,000 needs the full written contract. The old figure was $12,000, and it changed when the Building Work Contractors (Building Indemnity Insurance) Amendment Regulations 2025 commenced on 10 November 2025.
What section 28 demands
Section 28(1) sets seven requirements:
- the contract is in writing
- it sets out in full all the contractual terms
- it names the business the contractor trades under, the licence number and the names and licence numbers of any partners
- it complies with the Regulations on contents
- both the contractor and the owner sign it, personally or through an authorised agent
- the owner gets a copy of the signed contract as soon as reasonably practicable after both sign, together with the prescribed notice
- the copy and the notice are readily legible apart from signatures
The prescribed notice is Form 1, "Your building contract: your rights and obligations", set out in Schedule 3 of the Regulations. There is no day count on delivery. "As soon as reasonably practicable" is the test.
Warranties that survive the contract
Section 32(2) implies six warranties into every domestic building work contract with no value threshold at all, so they reach the $3,000 job as well as the $900,000 one. They cover proper workmanship to accepted trade standards and in accordance with the agreed plans, good and proper materials, compliance with statutory requirements, reasonable diligence where no completion period is stated, fitness for human habitation on a house and fitness for a purpose the owner made known.
Section 42 makes any purported exclusion, limitation, modification or waiver of them void. Not voidable. Void. Section 32(5) gives five years from completion to start proceedings, and s32(6) says that period may not be extended.
Insurance before the first dollar
Section 34 stops a contractor performing the work at all unless a complying building indemnity insurance policy is in force and the owner holds the insurance certificate. Division 3 catches domestic building work of $20,000 or more that needs development approval (s33(2) with reg 4).
Regulation 18(1)(b) fixes the minimum cover at $250,000 per dwelling for policies taken out on or after 10 November 2025, lifted from $80,000. SA.GOV.AU puts the practical rule plainly: work cannot start until the policy is taken out and both the owner and the council hold the certificate. Section 34 carries a maximum penalty of $100,000 for an individual and $500,000 for a body corporate.
What getting it wrong costs
Breaching s28(1) is an offence: $50,000 maximum for a natural person, $250,000 for a body corporate, with a $5,000 expiation fee.
The commercial hit is worse than the fine. Under s36(5)(b), if the builder has failed to comply with any requirement of Division 1 or Division 3, the owner's right to terminate does not close after five clear business days. It stays open until the work is complete. A missing Form 1 can hand the owner an exit on month nine of a twelve month build. Formality compliance is not paperwork in SA. It is the thing holding the contract together.
Citations
- [1]
Building Work Contractors Act 1995 (SA)
legislationSouth Australian Legislation · SA · accessed 16/07/2026
Section 28(1) lists the formal requirements for a domestic building work contract. Section 32(2) implies six statutory warranties. Section 42 voids any purported exclusion or waiver of them.
- [2]
Building Work Contractors Regulations 2011 (SA)
legislationSouth Australian Legislation · SA · accessed 16/07/2026
Regulation 4 prescribes $20,000 as the minor domestic building work sum. Regulation 18(1)(b) sets minimum cover at $250,000 for policies entered into on or after the prescribed day. Schedule 3 contains Form 1.
- [3]
Form 1: Your Building Contract: Your Rights and Obligations
governmentConsumer and Business Services (SA) · SA · accessed 16/07/2026
Notice under section 28(1)(f). You must have a written contract with your building work contractor, setting out all the terms and conditions of your agreement.
- [4]
governmentGovernment of South Australia · SA · accessed 16/07/2026
This is required for any domestic building work that must be approved by council and costs $20,000 or more. Building work cannot start until the insurance has been taken out and both you and the council have received a copy of the certificate.
- [5]
Greater protection for home builders
governmentConsumer and Business Services (SA) · SA · accessed 16/07/2026
Maximum insurance payouts to increase to $250,000 if a builder fails to deliver a finished home. The state government also intends to update the regulations to make it mandatory for all insurers to provide the increased cover.
How this was researched
This entry was drafted from primary Australian sources (legislation, regulator publications and industry guidance) and reviewed and signed off by Hunter Jacobs, Director, TradeForm. Citations link to the source documents you can verify yourself. The entry is re-verified on a cadence and automatically flagged for review when a watched source changes.